Final Turbine Installed at Yunlin Offshore Wind Farm in Taiwan
All 80 turbines have been installed at the 640 Yunlin offshore wind farm in Taiwan, being developed by Yunneng Wind Power Co. Ltd., a subsidiary of Skyborn Renewables.
Major offshore construction work at the Yunlin offshore wind farm started in December 2020 with the installation of the first monopile. The first of the project’s 80 Siemens Gamesa 8 MW wind turbines was installed in April 2021.
The 2024 offshore construction campaign commenced in March with the installation of monopiles following the winter break, and by September, all 80 monopiles and the accompanying transition pieces had been installed.
Fred. Olsen Windcarrier (FOWIC) and Shimizu collaborated to handle the transportation and installation of monopile foundations in 2024.
The wind turbine installation vessel (WTIV) Blue Wind, under a contract with FOWIC, was engaged as the installation vessel for both monopiles, in addition to the DLS-4200 of NMDC Energy, and wind turbines, in addition to Cadeler’s Wind Zaratan.